King Fire Update: The King Fire is currently at 82,018 acres with 10% containment. The following intersections are closed to the public: Mosquito Ridge at Gorman Ranch, Foresthill Divide at Soda Springs, and Foresthill Divide at Deadwood. IRONMAN cancellation supported by Placer County Health Officials. Public Information line is currently staffed at 530-886-5310 to handle inquiries. More »

Foresthill Transfer Station Upgrade Project

Foresthill Transfer Station 

Improvements Project

Project Description
The public tipping area at the Foresthill Transfer Station (FHTS) was constructed in 1984 and provides solid waste disposal services to approximately 6,000 Placer County residents in the Foresthill area. The public tipping area consists of four bays for tipping mixed garbage, two bays for tipping green waste, and other bins for electronic waste, appliances, metal, and tire disposal. Improvements will include new paving, retaining wall, fencing, drainage facilities, and relocation of the attendant booth with the goal of improving the public turn around area to relieve traffic congestion. In addition, this work will improve the quality of stormwater discharged from the FHTS.
(click here for project schedule)

Project Location
The FHTS is located at the end of Patent Road in Foresthill.

What to Expect

· Large trucks and construction equipment at FHTS

· Uneven driving surfaces at FHTS

· Possible increase in wait time

· Construction hours from 7:00 am to 5:00 pm, weekdays

Project Benefits

· Improved traffic flow, especially for trailers and longer vehicles

· Improved stormwater quality to comply with State permitting requirements


Point of Contact

Casey Ford, P.E.

(530) 886-4918
cford@placer.ca.gov

Project Schedule

· Mid-August 2012 - Early September 2012: Mobilization onto site, surveying and layout of improvements, and site preparation.

· September 2012 - October 2012: Complete site preparation, begin block wall, and install electrical and storm drain system.

· October 2012 - November 2012: Complete block wall, install aggregate base and concrete, and begin AC paving upper and lower levels.

· November 2012 – December 2012: Complete AC paving, install AC dike, fencing and gate, and complete project.