Kings Beach Costs and Schedule
Cost
The total project cost is estimated at $27.5 million. To date about $7 million has been secured for preliminary design and environmental review work. Placer County, Tahoe Regional Planning Agency (TRPA), and Caltrans are working closely with state and federal agencies in a collaborative effort to secure the remaining funds.
Schedule
Environmental Review Public Comment Board/Agency Approval |
Fall 2006 Late Fall 2006 |
| Engineering Design / Right-of-Way Acquisition |
Fall 2006 - February 2008 |
| Construction (pending available funding) |
June 2008 - October 2010 | |
| |
|