Construction Projects
Eastern Regional Materials Recovery Facility Concrete Floor Repairs
Proposed upgrades include repair reinforced concrete floor after the floor has deteriorated in locations of concentrated work equipment. The repair will increase longevity of the working surface and rideability. A portion of the work was completed in 2022 and the remaining work will be completed in 2023.
Foresthill Transfer Station Tipping Wall
Proposed upgrades include drainage improvements and minor grading/backfill. Improvements Improvements will reduce erosion that occurs from the disposal area. Work is anticipated to start in 2023 and be completed in October 2023.
Eastern Regional Materials Recover Facility Roof Repair
- Proposed upgrades may include repair of the damaged column to roof connection. The upgrades will allow work to be conducted in a safe manner and address damage that occurred to the structure.
- Work may be constructed during 2023.
SMD 1 Post Plant Improvements
Upgrades included new reinforced concrete dump station for pumper trucks. Improvements reduced operational costs based on location of disposal station. This $425,000 project was completed in November 2018
Meadow Vista Transfer Station Improvements
Upgrades included new landfill gas (LFG) well heads, decommission flare and free vent using new blower with VFD, and new LFG collection pipe. Improvements reduced operational costs based on low gas generated at facility. This $250,000 project was completed in August 2019.
Loomis Landfill Gas System Improvements Project
Upgrades included new decommission of flare and free vent using new blower with VFD, and new LFG discharge pipe and valves. Improvements reduced operational costs based on low gas generated at the facility. This $65,000 project was completed in April 2020.
Eastern Regional Landfill Improvements
Upgrades included constructing a stormwater treatment facility to collect runoff from the inert soil stockpile area. Improvements addressed State Water Board directive based on iron exceedances for permit compliance. This $700,000 project was completed in July 2021.