Construction Projects

  1. Current
  2. Planned
  3. Completed

Auburn Ravine Force Main Replacement

Replacing an aged 12-inch diameter asbestos cement pipe that conveys wastewater from the Auburn Ravine Lift Station to a gravity manhole on the State Route 49 trunk sewer line via Auburn Ravine Road and Marguerite Mine Road. The pipe is proposed to be installed using open trench construction entirely within the existing paved roadway right-of-way.  Horizontal directional drilling would be used to cross under two creeks, and open trench excavation with a bypass to cross under a third creek, all which cross Auburn Ravine Road.

A Mitigated Negative Declaration (MND) has been proposed and will be available for public review beginning November 25, 2019 and ending December 26, 2019 (see Notice of Intent for details), at the following locations:

Bell Road Lift Station Improvements

  • Replacing pumps, rails, receivers and control panel
  • This $160,000 project will take place in the summer and fall of 2018

Sylvan Glen Lift Station Improvements

  • Replacing pumps, valves and control panel
  • Acquiring easement on adjacent properties will increase the size of the existing easement and create pull-through capability and access on the shallow slope.
  • This $1.4 million construction project will take place in the spring and summer of 2018.

Sewer Maintenance District 1 Post Plant Improvements

  • Constructing a vactor dump station, fencing and a gate, and installing lighting
  • Current estimated cost is $350,000
  • Work to be completed in summer 2018