Construction Projects
Joerger Road Lift Station Improvement Project
- Proposed upgrades include pumps, rails, floats, wet well lid with safety grate, control and PG&E panels, electrical building, drainage improvements, flow meter and vault, asphalt paving and dike, earthwork, and antenna.
- Estimated cost is $572,252
- Work is anticipated to be completed in May 2023.
Sylvan Glen Lift Station Improvement Project
- Proposed upgrades include pumps, rails, floats, control panel, panel building, pump building, flow meter, bypass piping, force main piping, valves, wet well lid with safety grate, drainage improvements, gates, antenna, and access road.
- Estimated cost is $1,729,978
- A portion of the work was completed in 2018. Remaining work is projected to be completed in May 2023.
Winterhawk Lift Station Improvement Project
- Proposed upgrades included replace pumps, rails, floats, new wet well lid with safety grate, control and PG&E panels, drainage improvements, and asphalt pavement.
- Estimated cost is $250,000
- Work is anticipated to be completed in May 2023.
Highway 49 Upsizing Design Project
Project is currently in the design phase. Proposed upgrades may include extending the Auburn Ravine Force Main to the SMD 1 closed Plant sewer lift station to address capacity concerns in the existing gravity sewer line in North Auburn. The analysis and design is expected to continue through 2022. Work may be constructed during 2023 or when developer is conditioned to make improvements.
Wexford Lift Station Improvement Project
Proposed upgrades may include repair to the existing wet well, installation of a new wet well lid, new pumps/rails, new discharge pipe, new pump control panel, new meter panel, SCADA-RTU-antenna, updated dry utilities, arc flash analysis, electrical building, new piping/valves and upgrade to valve vault, new flow meter, generator, and Davitt crane sleeve and foundation. The improvements will address safety upgrades and aging equipment. Improvements may be constructed during FY 2023-24.
Magellan Lift Station Improvement Project
Proposed upgrades may include repair to the existing wet well, installation of a new wet well lid, new pumps/rails, new discharge pipe, new pump control panel, new meter panel, SCADA- RTU-antenna, updated dry utilities, arc flash analysis, electrical building, new piping/valves and upgrade to valve vault, new flow meter, generator, and Davitt crane sleeve & foundation. The improvements will address safety upgrades and aging equipment. Improvements may be constructed during FY 2023-24.
Petite Creek Lift Station Improvement Project
Upgrades included pumps, rails, floats, control panel, electrical building, emergency overflow storage, new valve vault, Davitt crane sleeve footing, and new paving. Completed in May 2017.
Vineyards Lift Station Improvement Project
Upgrades included replaced pumps, rails, and control panel and new Davitt crane sleeve and foundation. Completed in September 2019.
Bell Road Lift Station Improvement Project
Upgrades included PG&E power, control panel, lean-to structure, pumps, rails, discharge piping, and concrete apron. Completed in November 2019.
ERL Lift Station Improvement Project
Upgrades included re-route leachate force main, install new ARV and valve vault with flow meter, and replacing an existing leachate tank. Improvements minimized the risk of future SSO that had routinely occurred in winter months. Completed in November 2019.
Applegate 1 Lift Station Improvement Project
Upgrades included Smith & Loveless Lift Station Package replacement, relocate antenna/PG&E panel and poles, miscellaneous electrical, parking and drainage improvements, new generator, and asphalt paving to improve parking conditions. Completed in September 2020.
Auburn Ravine Force Main Replacement Improvement Project
Upgrades included replace sewer force main pipe, abandoned existing force main, valves, pavement repair, utility vaults, ARVs, design, and inspection. Completed in January 2021.
Edgewood Lift Station Improvement Project
Upgrades included replace generator, larger fuel LP tank, new concrete pad, and wet well lid with safety grate. Completed in March 2021.
Olive Grove Lift Station Improvement Project
Upgrades included pumps, rails, control panel, and wet well lid. Completed in March 2022.
Cavitt Stallman Lift Station Improvement Project
Proposed upgrades included purchase sewer easement, raise access, trenchless pipe repair, and repair inlet. A portion of the work was completed in 2021. Remaining work is projected to be completed in October 2022.