Details
- A slurry seal and new striping will be applied, April 2nd and 3rd, to the sections of the road that were impacted as part of the Project.
- The Clipper Gap Park and Ride will be closed on Tuesday, April 2nd, for resealing.
- Expect lane closures and traffic delays as a result.
- Construction of the pump station will be completed this month.
Details
- Construction of the pump station will continue this month.
- Asphalt paving on Applegate Road will be completed by March 5th and sealing and striping applications to the road are anticipated for later in the month.
Details
- Construction of the pump station will continue this month.
- Repaving of the impacted roadways, including the Clipper Gap Park and Ride, will take place when temperatures rise and provide better conditions for the finished product.
Details
- Connection of the force main to the boring section, on both the east and west side of I-80, is anticipated to take place in early January.
- The Clipper Gap Park and Ride will be closed the week of January the 14th, for open trenching activity.
- Installation of the force main along Applegate Road, including trenching and re-paving, as well as installation of air release and blow-off valves along the alignment should be complete by the end of the month.
- Construction of the pump station will continue this month.
Details
- Connection of the force main to the boring section is anticipated to take place in late December, requiring closure of the Clipper Gap Park and Ride for up to a week due to open trenching activity.
- Installation of the force main along Applegate Road, including trenching and re-paving, should be complete by the end of December.
- Installation of air release and blow-off valves will occur along the alignment this month.
- Construction of the pump station will continue this month.
Details
- Installation of the force main and paving, west of I-80 to Winchester, is complete.
- Installation of the force main along Applegate Road, between the new lift station at Merry Lane and the Clipper Gap Park and Ride, will continue through November and into the first weeks of December.
- Boring under I-80 is taking longer than originally anticipated by the contractor and is expected to be complete by mid-November.
- Construction of the pump station, described in the September update, will continue this month.
Details
- Installation of the force main along Applegate Road, between the new lift station at Merry Lane and the Clipper Gap Park and Ride, will continue over the next couple months. Work will include saw cutting and pipe installation.
- There will be a total road closure in at least one location this month on Applegate Road when the project goes under the railroad bridge; more details here as they are known.
- Boring under I-80 expected to be complete early this month, with connection to pipeline on Placer Hills Road.
- Paving will be complete over all newly installed pipelines from west side of I-80 to future connection point in Winchester by late October.
- Construction of the pump station, described in the September update, will continue this month.
Details
- Paving over the new force main from the west side of I-80 to Winchester will be completed in mid-September.
- Force main construction on Winchester Club Drive is anticipated to be completed in September. Work will include saw cutting and pipe installation; placement of Air Release Valves (ARV), Blow Off Valves (BOV), and repaving will begin in October.
- Installation of the force main along Applegate Road, between the new lift station at Merry Lane and the Clipper Gap Park and Ride, will begin on September 24th. Work will include saw cutting and pipe installation.
- There will be a total road closure in at least one location on Applegate Road when the project goes under the railroad bridge; more details here as they are known.
- Boring under I-80 will continue through September and into the first week of October. There are no anticipated traffic impacts to I-80, but the Clipper Gap Park and Ride will be closed at this time.
- Pump station construction activities this month include installation of a water well. Future construction includes completion of Wet Well installation, setting Emergency Storage Tank, preparing the site for the construction of the Chemical/Electrical Building, and installation of a Septic Tank.
Details
- Contractor will continue to trench, install sewer pipe, backfill and apply temporary paving on Placer Hills Road, from I-80 into Winchester, and along Winchester Club Drive. Saw cutting will also begin along Applegate Road from the Pump Station site at Merry Lane to the Clipper Gap Park and Ride bore site.
- The contractor anticipates beginning boring under I-80 the week of August 19 and continuing through mid-September. The Clipper Gap Park and Ride will be closed during this time. Traffic on I-80 will not be affected.
- Site preparation for the construction of the pump station at Merry Lane and Applegate Road will continue through mid-August. Construction of the pump station is anticipated to begin mid-August.
Details
- Construction activities in July will include saw cutting, trenching, sewer pipe installation and temporary paving between I-80 and Sugar Pine Road along Placer Hills Road.
- Site preparation for the construction of the pump station at Merry Lane and Applegate Road will begin in mid/late July.
Details
Beginning in mid-June, construction crews will begin locating utilities in the roadway by potholing (digging small holes in the road) along Placer Hills Road between I-80 and Sugar Pine Road, as well as saw cutting the roadway to prepare for trenching activities expected to begin in July.
Details
Placer County issued the Notice to T&S Construction Co, Inc. of Sacramento, California on May 7, 2012. Upon contractor's completion of required paperwork and materials delivery, construction is expected to begin in late May. More detail regarding work schedule and locations will be posted here as it becomes available.