The District issues two permits for a stationary source. The first - issued before construction begins - is an Authority to Construct. When construction is completed and Authority to Construct permit requirements are met, the District issues a Permit to Operate.
Authority to Construct (A/C)
The A/C permit allows construction of a new facility or the installation or the modification of equipment at an existing facility.
Inspection & Temporary Operation
Following construction, installation, or modification, District staff inspects the facility to ensure proper installation of all equipment. A temporary operating period is allowed for testing, calibration, and demonstration of compliance with conditions of the A/C.
Permit to Operate (P/O)
The P/O allows continued operation in accordance with all permit conditions and local, state, and federal air pollution requirements.
Re-Evaluation
The P/O is re-evaluated every year and is updated as necessary to ensure compliance and to reflect any changes to local, state, or federal requirements.